Thanks to the passage of Ballot Issue 5B in November 2018, LOTS of improvements will be made to our building. Phase 1: Summer 2019 - Dec. 2019 3rd Floor Remodel:
Update as of Dec. 18, 2019 - phase 1 is almost complete. Furniture will be moved in soon and classrooms will be ready for the Spring 2020 semester.
Phase 2A: 12/30/19 - 3/20-20 1st floor B Hall remodel All classrooms except 4 science rooms Phase 2B: 3/23/20 - 5/21/20 Remodel of 2 science classrooms, 2nd floor bridge classrooms and 2nd floor B Hall classrooms Update as of April 24: Construction is ahead of schedule. This is the new Creative Learning Space (Smart Lab): Phase 2C: 5/21/20-7/31/20 Remodel of all walkways, C wing, 2 more science classrooms, weight room, green room, public bathrooms and 2nd floor A wing. Photos as of July 30, 2020: Auxilary Gym: 1/3/20-9/18/20